cancel
Showing results for 
Search instead for 
Did you mean: 

Maintenance plans: massive restart in cycle

former_member680359
Discoverer
0 Kudos

We have performance-based maintenance plans and we will migrate them to SAP S4/HANA. Is there any way to replicate the exact same call dates with the same package sequence in the new system as per the old one?

These are two important characteristics of the maintenance plans:

  • Most of the plans are linked to a maintenance strategy that contain more than one package.
  • The main users usually modify most of the scheduling parameters for each plan (for example, the cycle modification factor) and the flag for the completion requirement is always set.

Is there a way to reschedule the maintenance plans in a massive way? I’ve been trying to use the FM MPLAN_START_CYCLE without success. Any suggestions?

Accepted Solutions (0)

Answers (0)