How set and build maintenance plan call date and planned date for every month last date?
Hey there,
The solution is already provided here:
https://community.sap.com/t5/enterprise-resource-planning-q-a/maintenance-plan-scheduling-by-key-dat...
I've checked it myself, and yes - it works.
What u gotta do in a nutshell in the Maintenance Plan setup:
1. Cycle and unit: 1 DAY
2. Scheduling indicator: Factory Calendar
3. Factory Calendar: AM
4. Scheduling period: doesn't matter, go with 3M if u want 3 month preview
5. Start of cycle: end of the month u select
Cheers,
Dan