Maintenance order schedule date

Jagadeeshpt
Explorer
0 Kudos
201

Hi Experts, 

We have business requirement  where the schedule start and finish date in the order should get adjusted as per factory calendar.

We are using factory calendar  in the work center having FRI and SAT as weekly off. if the schedule start date and finish date falls on any of the date that is either FRI or SAT then the system should move the schedule start and finish date to THRUSDAY. In case the basic start date is on any other days then the schedule start and finish date should not be change. 

View Entire Topic
preetirai1984
Participant
0 Kudos

Hi, There is no standard solution to move start and end date to back date when falling on specific day of the week. However, 

Please refer to this spro section and declaring work center factory calendar working days where you need work order, you can move work order generation to next working day.

Plant maintenance & customer service - maintenance and service processing - maintenance & service orders -

scheduling - set scheduling parameters - adjust scheduling - adjust dates

 

Regards,

Preeti