Hi All,

I am creating Maintenance Order with no. of operations. I have defined my work center from 6.00 AM to 2.00 PM as operating time. But in the Maintenance Order, start time is coming as 00.00.00 and end time as 10.00.00 in case of 10 hours for the 1st operation. what configuration I have to do to start from 06.00.00.

Kindly through your valuable inputs.

Regards,

Maheswaran.

Accepted Solutions (1)

Accepted Solutions (1)

former_member187991
Active Contributor
0 Kudos

hi

Kindly schedule and save the order then check the times ,also once again check the capacity to determine the start time

regards

thyagarajan

Answers (4)

Answers (4)

Former Member
0 Kudos

Hi Ramesh,

Kindly tell me what are the configurations required in OPL7.

Regards,

Maheswaran.

Former Member
0 Kudos

Hi Ramesh,

What kind of configuration to be done in OPL7.

Regards,

Maheswaran.

Former Member
0 Kudos

Hi,

I have tried those. But no improvement.

Regards,

Maheswaran.

Former Member
0 Kudos

Hi Maheshwaram,

Please check Your Work centre Data at IR03. For Start / Finish/ Brake Etc.at capacity Tab.

Also sure for finite sheduling tab.

Then make sure You have OPL7 Configuration step.

You shold able to get the time from above inputs in your order.

Regards,

Ramesh

Former Member
0 Kudos

Hi Thyagarajan,

Thank you for your reply. Can you please tell me how to schedule the order. I have saved that order & then only checked. Still same issue.

Kindly tell me the steps with the tcodes so that I can follow your idea clearly.

I am looking forward your reply.

Regards,

Maheswaran.

former_member187991
Active Contributor
0 Kudos

hi

In normal case scheduling will be done autoamtically .if not then use Ctl+F4 to schedule and see the dates .also ensure the capacity defined to the work center

regards

thyagarajan