Maintenance Item Have Different Start Cycle

Ariel09
Explorer
0 Kudos
98

Dear Experts,

Our customer have requirement to create maintenance plan time based. We already test and explore it and we have a question.

Can we have a different start cycle for every maintenance item ? for example : in Maintenance Plan 1 we have 3 Maintenance Items with different Technical Object/Equipment. We want to have every maintenance item to have a different start cycle. Any suggestion to this case ?

Thank You!

SAP S/4HANA Cloud Public Edition SAP S/4HANA Cloud Public Edition Asset Management 

View Entire Topic
Vaibhav-Mishra
Active Participant
0 Kudos

hello @Ariel09 ,

Maintenance cycle is assigned to the header of maintenance plan. If you want a different cycle for each maintenance item then create a separate plan for each item. I am assuming that you have different equipment with each maintenance item. 

Assignment of maintenance cycle to item is not available.

Vaibhav Mishra