on 2024 Sep 10 6:31 PM
Hi Team,
We have a Maintenance Plan of the cycle of 1 Year, start of cycle - 01/05/2022 and Call Horizon is 30 Days. There are no shift factors or Tolerance set up. For this year why the work order got created automatically on 29/03/2024 instead of 01/04/2024.
Regards,
Preethi
Hi Preethi,
Could you check the calculation log for the generated call object?
You will find this particular call in the plan, where you can choose the specific call and see the calculation details. Here you will find the date calculation details.
I am not sure, but also check if there is an impact of the leap year.
Regards,
Vijay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
8 | |
7 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.