Maintain Scrap with out MRP in PP_PI

srinivas_s7
Participant
0 Kudos

Hi,

Here is my scenario.

We are working for process industries,where in we are not having MRP planning ,

So client wants to trace the Scrap ,post confirmation using MCP5(report).

Say for example:

If i created a process order for 100 ea,and want to confirm the scrap say 10 ea with cor6n,with final confirmation of only 90 ea(100-10).

Note :when i tried using Cor6n,system dint allow to enter the scrap for the phase confirmation..

i even tried maintaining the component scrap ,but of no use..

Thanks,

Raj

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Dear rajan,

in COR6N u can confirnm only operation scarp, ur component scrap will not have any role it is only for planning.in Cor6n if u 2 operations to confirm and ur order qty is 100.

frist operation ur yeild is 95 and scrap is 5

second operation your yiels will be 92 and srap will be 3 like this u have to confirm

i.e. ur yeild + scrap is equal or less than than the ordwer qty for 1st operation and for second opertion it should be less or equal to frist operation yeild

sree

Answers (2)

Answers (2)

srinivas_s7
Participant
0 Kudos

Dear Friends ,

Thanks for the support,as u guys said their was the correction with order dependendent parameters COR4 and also the scarap qty and confirmed qty should be equal to order qty.

it working now,the report MCP5 is fetching the scarp qty confirmed using COR6N.

Please allow me in your groups.

Regards,

Rajan

dhaval_choksi3
Active Contributor
0 Kudos

Hi,

Go to COR4(Order type Dependent parameter) select your Order type along with Plant and in Planing screen make tick active for Scrap .

Regards,

Dhaval