Hi All,

I have created a LSMW with batch input recording method for physical inventory and I have give access to the users so that they can do the activity but I dont want to give them the access of creating a new LSMW there in production

Question :Please suggets how to restrict the users from creating new LSMW in production but at the same time they should be able to use the existing LSMW in system .

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

SAP,

Use the standard authorization objects for LSMW.

B_LSMW should probably have activities 03, 10, and 16 for end users (display, post, execute, but not create nor change).

You can further prevent users from executing the 'wrong' project by only giving them access to 'their own' projects. object B_LSMW_PRO, enter the names of the projects you wish them to have access to. No asterisks.

Talk to your basis/security team. They should have no problem with this.

Best Regards,

DB49

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

the better way to control this would be to create BDC program with a tocde.