on 2020 Apr 13 2:51 PM
Hello I am work in my plant and they required implement maintenance order (PM) with information of logistics time and the time consumed to complete the maintenance.
Is there any add on in SAP for logistics time? Or I am n´t see where complete this information.
When I talk about logistics times, I mean mobility times and any other time other than maintenance itself.
Thank you.
Request clarification before answering.
Hello Ulises:
You can add additional operations to the order with a specific work center to follow up the travel time to get to the maintenance side. You can then create confirmations for those operations to show the real time used for the movement and even estimate the cost using an activity type.
Have a nice day,
Jimena
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
53 | |
8 | |
8 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.