List Independent Requirements (VSF)

Former Member
0 Kudos

Hi All,

I am looking for a transaction where I can list independent requirements for a range of materials. I know of MD62, but you can only enter this transaction with one material number. There must be another transaction for displaying lists of independent requirements with several materials.

Regards,

Dag

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Try MD74

Enter the Plant, Material (Range), Key Date

Check - record history

Uncheck - Delete inactive version before key date

Check - Create list

Check - Test Mode (only if you want to check the list)

Let me know if this helps.

Anupam1143
Active Contributor
0 Kudos

Hi

You can check table PBID and PBHI

hope it will works for you

Regards

Former Member
0 Kudos

MD62 has two more options for selection

Product Group

Rrequirement plan no

MD73 also has two more options

Product Group

MRP Controller

and Requirement PLan no.

By selecting any of the above, the list of materials with PIR's will appear.

Regards

Ratan

Former Member
0 Kudos

Thanks for your reply. Hoewer MD73 does not really help me.

In MD62 you can see you material to your left and in the columns on the right you can see your forecast in each time-bucket. In MD73 you only get a list of the materials, not of the actual values for the planned independent requirements...

Any other suggestions - help would be much appreciated!

/Dag.

Former Member
0 Kudos

MD62, go for Product group or requirement plan option , you can create or edit the PIR's

MD73 is a report, when the materials list comes, select the required materials ,you will find the PIR's in the report

regards

Ratan

Former Member
0 Kudos

Hi dag,

You can take list of PIRs from table PBIM , there you can select multiple materials as well as req type too

thanks