Dear Gurus,

The scenario is if we do the final confirmation of last operation with the quantity less than the order quantity then system should not allow to do the GR of production order with the order quantity or the quantity more than the final confirmation quantity. Please provide solutions.

Regards,

SAP CONS

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

I hope you are using Auto GR functionality then you can use following config to restrict incorrect GR with confirmation :

Go to OPK4 ---> Select Your plant & order type ---> Go to Individual Entry General tab page

There you need to maintain tick in check boxes *Goods Movements & Termination of Incorrect Goods Movements*.

This will fulfill your requirement of linking confirmation & GR.

Check & revert if any issue.

Regards,

Tejas

Answers (4)

Answers (4)

Former Member
0 Kudos

User Exit - MBCF0002

It will check data from AFRU table

Provide the user exit to your Abaper, he will do the needful

Former Member
0 Kudos

Hi ,

If you are not posting complete qty is last operation, why are you setting FInal Confirmation? It should be APartial Confirmation only.

Also check OPK4 settings for overdelivery/underdelivery and incorrect goods movement .

If nothing help, you need to use USER exit to control the GR.

Edited by: santosh sarda on Jun 22, 2011 6:51 PM

Former Member
0 Kudos

Dear Sir

Please go thrugh "Parameters for order Confirmation"..Go to Check Tabs, select Underdelivery and ocer delicvery as

" X Error when Quamtaty falls below Under delivery tolerance and "X Error when Quananty is exceed over delivery tolerance.

Also maintain in Worksechduiling Tolerance Tab, Define as "0" Tolerance .Hope so this will full fill yours requirement

Also go to "Individaul Entry General" Goto " Error Handling /Logs" Tick on Good movements and "termination of Incorrect Goods Movements".

Regards

Bhupendra Singh

Edited by: laxmi23101975 on Jun 22, 2011 12:19 PM

former_member1362664
Contributor
0 Kudos

Hi.

Go to the OPK4.

DO required setting in Checks area for controlling of over delivery.

Regards

Vivek