Link between Suboperation in Task list and Maintenance Item

preethialevarthi
Participant
0 Kudos

Hi Team,

Can you please let me know any table to link Suboperation in Task list with Maintenance Plan.

Like based on equipment assigned in Suboperation in Task list i need to find the maintenance Plan.

Regards,

Preeti

preethialevarthi
Participant
0 Kudos

Hi Vaibhav,

Thank You for the input.

But can you please let me know how do we get PLNAL?

In PLPO table we don't have PLNAL field.

Vaibhav-Mishra
Active Participant
0 Kudos

Hello Preeti,

This will help you.

PLPO-VPLAL = PLKO-PLNAL => (Group counter of the referenced task list)

Vaibhav

Accepted Solutions (0)

Answers (1)

Answers (1)

Vaibhav-Mishra
Active Participant
0 Kudos

Hi,

Please try with table PLPO and MPOS. The field VORNR in PLPO is a sub operation if the value of SUMNR is more than Zero. In MPOS, you can use fields PLNTY, PLNNR, PLNAL to establist link between Task List number, maintenance item and maintenance plan.

Try this in SE11 and SE16N.