Hi,

Can you please tell me the link between BOM, Work Center and Alternate Production Version(PSA).

In my requirement i have to check whether the Parent material PSA is same as the child material PSA.How to check out this?

Regards,

Uday

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Uday,

No it is not possible to check like that

only link between BOM and Work center is Production version ....BOM and Routing ..and routing will have workcenter

Thanks