on 2009 Jul 28 12:50 PM
Dear All,
My client is asking one advice , it is as follows,
Can we copy the one version to a new version ( Eg V0 to Z1) with the exsisting labour rates & hours of version 0
I feel version will copy only the layout and not the values.... values are to be updated as per the updated run.
Please let me know the other opinions also ...
I am new to controlling
Thanks in advance'
Arun R
Request clarification before answering.
Hi Arun,
You can use transaction KP97 to do the copying. It copies the entire plan values including Activity prices , Hours , Statistical Key figures etc., On the initial screen of KP97 the details like the source plan data types are not visible. You will have to press the button "Selection" under the Plan data section. In that selection , you can select which all data you want to transfer from One version to the Other version.
Regards,
Venkat.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
96 | |
39 | |
7 | |
6 | |
5 | |
3 | |
3 | |
3 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.