KKS2

Former Member
0 Kudos

Dear Experts,

While running T.code kks2 i am getting the following error.

@0A@ E KV 177 1 ORD 30000240 1 The target cost version is not intended for variance calculation Target Costs: Determine Valuation Basis

@0A@ E KV 176 1 ORD 30000240 1 Cannot calculate target costs Calculate Target Costs

How to resolve this problem.

Thanks in advance

regards

avudaiappan

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member188826
Active Contributor
0 Kudos

In OKV6 the target cost version need to be maintained for your controlling area.

When you run KKS2, you may specify the version (instead of selecting All version) for which the config is maintained.