on 2012 Apr 15 7:17 AM
hi,
may i know what is the purpose of ke4r?
to assign each of the cost component to particular value field?
thanks
Yes, it is to assign components of cost component structure, to value fields.
With this assignment, values from the respective cost component ( in CO-PC ) will be displayed in value fields in CO-PA.