Issuing material to production order

Former Member
0 Kudos
126

The scenario is as follows:

The production order is assigned to a WBS element. Material exists in un-restricted use stock (not project stock) and we need to issue this material to the production order. I tried to use CO27 and MB26, however both demand project stock. Is there a configuration step I need to make this work? IT doesn't make sense that I have to move the stock from unrestricted use to project stock before being allowed to issue it to my order...

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

Have you tried MB1A with mvt type 261?

regards

Srinivas

Former Member
0 Kudos

Hi Srinivas,

Yes I have actually, but the problem lies with CO27.

I ended up getting my answer on another forum and so here it is:

Since this is a production order created without a material header using a WBS element, the system assumed I would always issue from project stock. Although this is usually the case, in the odd case where it is different, you need to change the special stock indicator in the order to blank (since it defaults to 2).

I would have though the indiv/coll indicator in the material master would have been the master in populating this field, instead it was the fact that i created the order with a WBS element that became the master.

Thanks anyway!

Maria