Issue in Maintenance Plan - Key Date

former_member806758
Participant
0 Kudos

Dear Friends,

I had a Issue in "Maintenance Plan - Key Date".

My Client Requirement is Every month at same date order should be trigerred.

Everything is fine with Key Date till date 28th of any month.

For 29, 30 & 31 we facing problem.....

For Eg:

Call horizon :  90  %

Scheduling period : 1 Yrs

Start of cycle  :  30.11.2013

After scheduling

Call NumberPlan DateCall Date
130.12.201327.12.2013
230.01.201427.01.2014
328.02.201425.02.2014
428.03.201425.03.2014
528.04.201425.04.2014
628.05.201425.05.2014
728.06.201425.06.2014
828.07.201425.07.2014
928.08.201425.08.2014
1028.09.201425.09.2014
1128.10.201425.10.2014
1228.11.201425.11.2014

My Problem is after February all Plan date comes to 28th of the corresponding months.

What is the solution for this issue???

Regards

Mohan

Accepted Solutions (0)

Answers (4)

Answers (4)

former_member196951
Active Participant
0 Kudos

Hi MK DG

If your have got the satisfied answer, please close the query with mark on Correct/Helpful Answer and Like. Thanks a lot and waiting for more discussions..

parveenG

former_member200331
Contributor
0 Kudos

Hi MohanaKrishna,

Everything is fine from your end... Please follow the instructions given by Praveen Goyal and Also check if your Scheduling Indicator is set to : Time-Key Date as it will focus on exact date of your plan.

Also keep in mind that, to set this indicator, you need to have your frequency (in case of Strategy based plan) or Cycle length (in case of single cycle plan) needs to be in multiple of Month or year.

Hope this helps....Please check and revert.

Chin2.

kalyan_chakravarthi6
Active Participant
0 Kudos

Hi,

Since you are giving 29th or 30th as start of cycle and for Feb 2014 is having 28 days system is taking the last date of Feb (28.02.2014) and scheduling for other months accordingly.

I think this is SAP program error, better to raise OSS message.

Thanks,

Best Regards

Kalyan

sebastian_lenartowicz
Active Contributor
0 Kudos

I support Kaylan about the OSS note - I was able to replicate your issue easily, it is SAP standard behaviour.

Also, the unit of measure is not relevant, as long as the cycle is a multiple of month (i.e. n*30 days)

former_member196951
Active Participant
0 Kudos

1. First of all check with plan -cycle/unit- if it is 30 Days, replace it with 1 Month.

And

2. remove the call horizon, if allowed to your requirement.

3. start with cycle date (as reqd. orders release date)  -28.11.13 or 27.11.13

4. it means both plan date and call date will be same & fixed.

refer the attached snapshots.

Message was edited for further solution by: parveen goyal

sebastian_lenartowicz
Active Contributor
0 Kudos

Greetings Mohan,

Follow Parveen's advice, also, you may want to use the "Fix call" option in IP10 to fine-tune the date for March, or restart the plan for March from 29th/30th/31st  in the same t-code.