Is there a process for moving costs from maintenance work orders to capital projects?

We have reversed the settlements on the work orders, and then trying to put the relevant NWA in , then receive error message :

Rule for allocation of PM order to PS network is not maintained.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

hi

check the allocation structure and the settlement related customization settings.