Is it possible to influence the account used for the OPSV planned cost for PP via exit or similar?

anders_loven
Explorer
0 Kudos
347

Hi all.

In a PS scenario with assigned production orders we get planned cost from the production orders appended to the project after checking the box for that in OPSV and executing a network costing.

It seems the account used for the planned cost comes from the settings in OBYC.

Is there a way of influencing / overriding the account used for this?

Thanks / Anders

View Entire Topic
anders_loven
Explorer
0 Kudos

Following up on the above. I looked at this together with an ABAP:er but we could not see a way of updating the account used for the planned costs via the strategy U option.