on 2024 Jul 03 12:17 PM
Hi
SAP S4HANA Public cloud.
I am working with process order and QM at the end (after GR).
QC checks thet there is a must to create rework order to fix a batch.
IS it possible to create rework order in process manufacturing? I have seen rework for production order.
What should be set for such a production?
Regards
MAciej
There is a scope item "Rework Processing - Stock-Manufactured Material (BJN)", you can follow this scope item.
https://me.sap.com/processnavigator/SolS/EARL_SolS-013/2308/SolP/BJN?region=DE
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.