on 2008 Apr 18 5:21 AM
Hi all,
Is it possible to chnge the Valid from date of the BOM?
If NO then what could be done to chnge the valid from date of the BOM?
Hi,
You can not change the valid from date to BOM.
You have to implement Engineering Change Management to apply this.
Regards,
Dharma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Chetan,
It is not possible to change the valid from date of the BOM.
If you use ECM and implement Revision Level, Based on the Revision Level you can have the diffrent BOM valid from dates effective.
Regards,
Siva
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.