Hi,

I'm trying to set up simple availability control for Internal Orders. I activated Order Management for the controlling area, went through the customizing for the Order Type, Budget Profile, and Settlement, defined the Model Order, and set up Availability Control.

My problem is that when costs are posted to an internal order, the budget limit that should give a warning and email instead gives an error. Here is an example of test values:

COAr - 0010

Tr. Grp - ++

Act. - 1

Usage in % - 80.00

COAr - 0010

Tr. Grp - ++

Act. - 2

Usage in % - 95.00

I have no activity type of 3 defined. I correctly recieve a yellow warning at 80% of budget, but as soon as I hit 95% I recieve an error with the text "Item 001 Order 1RCER2010003 budget almost exhausted." Although it says the assigned funds are less than the budget, it is a red error, and so I cannot post the cost, and no email is sent to the person responsible. I have not been able to find what configuration I have done wrong. Thanks for any help you can give!

Thanks,

J

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi J,

from my experience the cause of the problem is that the budget manager has not been correctly maintained - i.e. if the system cannot find the BM it resorts to Act. 3. Did you maintain the BM via OK14 or just in the order master data?

Regards

Karl

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Karl,

That was definately the problem. I skipped that step when going from the sandbox to development. And it makes sense why SAP would choose to stop the posting if it can't warn anyone.

Thanks so much for the reply, it saved me a lot of headaches.