Hi all

While try to create the semi finish material , in the mrp view 4 , the indicator for the material is not taken for the collective indicator . it take only the individual indicator

the error shown as

ONLY INDIVIDUAL PLANNING POSSIBLE( NO QTY-BASED INVENTORY MGNT)

WHAT I AN DO CHOOSE THE COLLECTIVE INDICATOR

THANKS

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member335796
Active Contributor
0 Kudos

Hi,

What is the planning Strategy maintained for this Material?

Regards,

Siva

Former Member
0 Kudos

hi. siva

i do not use the planning strategy or the semi fini matrl

but for fert i used 10 as the plnn strategy and this is bom header to the semi fini

Former Member
0 Kudos

Hi,

Check in tcode OMS2.

Check for the semi finished material type, Qty update tick is there or not.

Regards,