Incorrect component in production order by MRP

Former Member
0 Kudos
83

On conversion of production order via MRP, in production order one of the component is incorrect with reference to BOM where

as on creation of PO manually by T code CO01 the component is correct even in planned order too it is correct by manually.

suggest any clue for the above.

Edited by: jayalakshmi999 on Mar 5, 2011 12:52 PM

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member196530
Active Contributor
0 Kudos

Dear ,

Please check the following :

1.BOM validity and componenet valididty while MRP run .Basically , during MRP run , system cheks set up in MPR4 view -BOM Selection and Explosion Indicator and then explode the BOM with its compoenet having correct valididty date .If the componenet does not have correct valididty (From and To date ) , then BOM may be selected without this compoenet and generate planned order as well as subsequenetly , carried out the same in Production Order .

2.In case of Direct PO , you have Production Order Basic Finish and Start date which comply with the BOM Valaidty including this component so system will copy the BOM along with all the component listed inside .

3.If you are maintaining PVs with differenr BOM Alternative and routing with Lot size and valaidty , if it is not matching according to MRP4-2/3 indicator in BOM Slection /Explosion methods , then it may selecting the other alternative not having thew companet listed .

Check in test system and come back

Regards

JH

Just check in the

Former Member
0 Kudos

Hi,

When you coenvert planned order to production order check what date is used for bom explosion, you bom may be different for that date.

when you cerate order using co01 , u kight be using different dates than planned order and hence it explodes correct bom.

check and revert,