How to Transport a Factory Calender

Former Member
0 Kudos

Hi All,

I had done a small change to Holiday calender in SCAL. I have read that it's not suggestive to transport it. Can any one let me know the procedure to transport the change to QTY and PRD systems.

The transport button is greyed out .

Best Regards,

Sri

View Entire Topic
Former Member
0 Kudos

Transport the Factory calendar

Changes to calendar data are not automatically included in a correction request.

For the calendar data to be utilizable in another system, use the function Transport in the initial screen of the maintenance transaction.

Note that you cannot transport individual public holidays or calendars. You can only transport calendar data in its entirety. When you do this, all public holidays, public holiday and factory calendars existing in the target system are deleted.

please come back if required.

Former Member
0 Kudos

Hello rajesha,

I had created a new calender entry Z1 with a few setings. I want to transport only this one entry and not all. How do we make this transport of a single entry. I am aware of the transport Icon which imports all the public holidays and all calenders to next systems.

Regards,

Sri

Former Member
0 Kudos

The following OSS Notes have also been checked.

356483 : Customizing: Current settings in the test system.

077430 : Customizing: Current settings .

328916 : Cust Changes despite "System cannot be changed" setting

Can any one provide an input on the procedure to move a factory calender - Individual entry..

Thanks in advance