How to setup factory calender in SAP for annual Shutdown

shreekumar
Participant
0 Kudos

Dear Experts,

The client's plant will shut down from 19-12-2020 to 10-01-2021 for maintenance.

Kindly assist how to set up the annual shutdown in the SAP factory calendar.

Regards,

Shreekumar

peter_atkin
Active Contributor

Shreekumar,

For my intrerest, why do you need a factory calendar for a shutdown?

PeteA

Accepted Solutions (1)

Accepted Solutions (1)

Alexand3r
Participant
0 Kudos

Hi,

use transaction SCAL --> Factory calendar --> Choose your valid factory calendar for the plant --> double click --> maintain your closing days in the option "special rules".

shreekumar
Participant
0 Kudos

Thank you sir for your response.