We have projects managed in SAP-PS, where each SAP-PS project collects construction costs and is settled to an Asset Under Construction (AUC). Once the project is completed and sold, we need to settle the AUC to an internal statistical order to calculate specific costs required by the financial team. Ultimately, these costs should be posted to a cost center.
To achieve this, we use the settlement rule ORD with the statistical internal order (IO) number. However, when settling through CJ88, the system directly settles the AUC to the cost center of the IO and does not post to the statistical IO at all. Is there a way to ensure that the system posts to the statistical IO?
Thanks in advance
As I know, settling an Asset Under Construction (AUC) to a statistical internal order isn't standard. It's typically settled to a real internal order or cost center.
I guess the best will be to ask SAP consulting team for clear answer or a workaround.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
8 | |
6 | |
5 | |
5 | |
5 | |
5 | |
5 | |
4 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.