How to Set Up the MRP SAP Planning Horizon

0 Kudos
773

Working as the MRP type V1, how and what parameters must be changed so that the planning horizon is greater than the lead time of the material.

View Entire Topic
rob_mm
Active Participant
0 Kudos

caio,

You can define the Planning horizon in number of days in tcode OPPQ and/or in OPPR, to be greater than the lead time of the material configured in the MPR views.

If this help to address your topic, please kindly accept the answer.

Best, Ro.

0 Kudos

Hi Roberto, thank you for your answer ! But this set up is valid for materials that extern supply ?

best regards

rob_mm
Active Participant
0 Kudos
caio,Yes, for external supply you take those infos inconsideration: Procurement lead time = Planned delivery time + GR Processing time MA

If this help to address your topic, please kindly accept the answer.

Best, Ro.