Working as the MRP type V1, how and what parameters must be changed so that the planning horizon is greater than the lead time of the material.
Request clarification before answering.
caio,
You can define the Planning horizon in number of days in tcode OPPQ and/or in OPPR, to be greater than the lead time of the material configured in the MPR views.
If this help to address your topic, please kindly accept the answer.
Best, Ro.