How to set Production Version as default in costing 1 tab for the cost estimate purpose

Former Member
0 Kudos

Dear all,

we have multiple (3) production versions for the one material, for the cost estimate, need to pick second one PV:

How to set Production Version as default in costing 1 tab for the cost estimate purpose.

Thank you,

Regards,

Raja

Accepted Solutions (1)

Accepted Solutions (1)

former_member198650
Active Contributor
0 Kudos

Hi,

Lock the versions which you do not want and also check the validity maintained for active one. If you done correct settings, then at the time of cost estimation it will pick the active version automatically.

Regards,

Mukthar

Former Member
0 Kudos

Thank you Mukthar.

Is there any other way to get the required production version without Locking the unused production versions.

Thank you,

Regards,

Raja

Answers (1)

Answers (1)

former_member198650
Active Contributor
0 Kudos

Hi Raja,

You can restrict it through validity also.

Regards,

Mukthar

Former Member
0 Kudos

Thank you very much for your help.