Hi All

When creating the PO, if we do not set the PIR for order confirmation and acknowledge, we must specify (check) line by line, right?

Is there any way to set them in header PO so we will not select line by line ?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

You can use PO mass maintenance transaction MEMASSPO to enter Confirmation Control at Item level.

Regards,

Answers (1)

Answers (1)

JL23
Active Contributor
0 Kudos

No there is no option at header level, but there is a Fast Change option for items. It is an icon below the item overview that looks like a movie strip

Explained here as well:

http://help.sap.com/erp2005_ehp_05/helpdata/en/87/3a8f73d49c11d3b58a006094b9476a/content.htm