0 Kudos

Supply chain has loaded the demand as PIR, so after Procuring and inwarding, i created a sales order and w.r.t. Sales order, delivery is created, now i want as soon as delivery is created, the demand (PIR) should get reduced reduced by that same amount. Pls tell me how to achieve the same

Accepted Solutions (1)

Accepted Solutions (1)

former_member185450
Active Contributor
0 Kudos

Hello Satish,

As per your requirement if you have done the PGI (601 Movement) your independent requirement has to reduce

so please activate the tick mark with 601 movement type OMJJ-->Update control--> Ind.Rqmts Reduction

Then run one cycle and observe the results

Regards,

Venkatesh..

Former Member
0 Kudos

Thank you venkatesh

its working. But I have one more doubt. I have defined a BOM for this FG, which is a trading goods. But we are doing packing without any production order. So my client requires planning for the dependent requirements also. But after loading PIR, the subsequent dependent rqmnts (for child items) are not getting generated.

Pls help.

Regards

Satish

Answers (2)

Answers (2)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

I suggest you to read carefully the notes listed on the document below:

BR
Caetano

Former Member
0 Kudos

Hi Satish,

You can try to use strategy 10. This strategy reduces the PIRs at goods issue for sales order.

For further details, please see the following link:

Net Requirements Planning (10) - Demand Management (PP-MP-DEM) - SAP Library

Kind regards,

Marcos

Former Member
0 Kudos

Hello,

The document is not accessible, it needs login credentials

Regards

Satish

UmeshMali4994
Active Contributor
0 Kudos

Hello Satish,

Please check the planning strategy 40 for your scenario.

Planning Strategy consider PIR as well as Sales order, and Incoming sale order consume the PIR as per Consumption mode and period setting.

Set planning strategy 40 in MRP3 view and set Consumption mode and period as per your requirement.

Check below link for Planning strategy 40  

How Strategy 40 - Planning with Final Assembly Works

I hope this information helpful to you