on 2022 Sep 02 1:56 PM
Hi All
We are assigning the materials to the internal activity it a stock item after releasing the WBS store user will draw the materials. We facing one issue some users are changing the required quantity and they are drawing more quantity
How to prevent changing the required material requirement quantity which is assigned to the internal activity material component
I have checked validation and user status I have not found anything related to the material quantity
Thanks
Praveen
Request clarification before answering.
My question is clear
How to stop if the user changes the quantity after drawing the materials from the stores? The user is changing the quantity from T-code: CJ20n
If I change the quantity where the system is just giving the above information message.
We have used the user exit CNEX0038 but the breakpoint is not triggering
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
9 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.