How to link the PS & PM modules

Former Member
0 Kudos
437

Hi Friends,

We want to integrate the PS module with PM module.

We have to link equipment no of PM to WBS element of PS.

Will it be possible ? If yes please suggest the procedure.

Regards,

Pradip

View Entire Topic
alpesh_saparia3
Active Contributor
0 Kudos

Hi,

You can integrate PM with PS.

You can assign WBS element in equipment master in Organisation Tab.