how to issue material or component phase wise at the time of process order confirmation.

example:- we have one operation and three phase and there are three component and we require issue a material to a phase.

Accepted Solutions (0)

Answers (1)

Answers (1)

Anupam1143
Active Contributor
0 Kudos

Hi

You can assign the material to the phases in master recipe and while confirming the same through COR6N , you can issue or backflush the goods

check this link

http://help.sap.com/saphelp_46c/helpdata/en/89/a424ac461e11d182b50000e829fbfe/content.htm

Regards,

Anupam Sharma

0 Kudos

Yes sir , as per  you i assign material/component to phase  but when i do confirmation by cor6n than its give error

Phase/operation in process order 1000025 does not exist (please check entry)