How to inherit attached documents from Work Scheduling to PM work order

javierlopez
Explorer
0 Kudos

Hello.

At the time of creating a PM work order (IP30 or IP10), how can I set the system in order to inherit attached documents from work scheduling to work order?

Thanks in advance,

Javier Lopez

Accepted Solutions (0)

Answers (1)

Answers (1)

NTeunckens
Active Contributor
0 Kudos

If you are using a TaskList, you could see if you can activate Business Function "LOG_EAM_VE_INT" to enable adding Attachments / Documents to the TaskList. Upon WorkOrder-creation through TaskList, the documents should also be transferred.

See SAP-Note 1821916 and SAP-Help for more Details ...


Hope this helps

Nic T.