How to exclude shutdown period for MRP for a warehouse, or for a specific material group

0 Kudos

Dear All,

We have fairly big operation with several warehouses and plants. During the summer shutdown one of our warehouse shuts down. We would like to run MRP considering this shutdown to generate purchase requisitions, before shutdown period. It's important that some of our warehouses will and should recieve.

Is there a warehouse specific solution for this?

Accepted Solutions (1)

Accepted Solutions (1)

DominikTylczyn
Active Contributor

Hello terdyp

MRP is executed on a plant (MRP area) level, not on a warehouse level. You can model a plant shutdown period with the factory calendar by putting the days off there.

Best regards

Dominik Tylczynski

Answers (1)

Answers (1)

Ritz
Active Contributor
0 Kudos
terdyp

Please provide more details when you create PR before shut down.

If its just the question of quantity required to be supplied from warehouse, create planning considering the period and quantity.

Thanks

RD

0 Kudos

Dear Ritesh,

We are running the MRP for external requisitions and would like to avoid the MRP to generate deliveries during the shutdown period to the warehouse.