Hi All,

I'm doing Subcontracting process Im sending ROH material and getting ROH material,

Im not maintaining BOM.

I have to enter component material manually and what is the exactly requirement date here. requirement date is Subcontractor should should receive material before requirement date..

Please tell me what is the requirement date exactly, how it will calculate

thanks and regards..

ramesh reddy

View Entire Topic
Former Member
0 Kudos

Hello ramesh,

If BOM is used you will have to enter the dates for the components which will provide you with the requirement date automatically.In the above mentioned scenario you are not using BOM.

Requirement date is the components or the raw material are availiable at your stock on the required date mentioned.

You can determine whether the components are available on the date required by selecting Edit -> Availability check. in the subcontracting order.

Calculation of requirement happens automatically if you use BOM.Else you have to give it manually.