Hi SAP Gurus,

I am in Fund Management - BCS ( ECC 6.0 ) configuration.

My client want Period-wise Budget.

For that, I have activated " Activate Period Control".

Then, while giving Budget in FMBB, it askes Distribution Key ( DK ), I selected SAP standard No 1 for "Equal Distribution".

When i save the budget- in FMBB, the Distribution Key coloumn is vanished.

Now my question, Why the Distribution Key coloumn is vanished? System accept the 11 month Budget for 12 month why?

Kdly Advise me for solution....

regs / Devi Aparna

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Eli,

Thanks for your instant reply.

Have checked the SDN for period - wise budget.

Could not catch the right answer. Could you please provide me a link. So that, i can put full stop on my issue...

regs / Devi Aparna

iklovski
Active Contributor
0 Kudos

Hi,

Period control has nothing to do with budget period-wise management. Please, search SDN for this issue; the soltuion has been described several times. Regarding the distribution key, you should check the layout definition in FMBB.

Regards,

Eli