on 2009 Feb 25 1:17 PM
Dear All
Dependent requirement created for subitem need to be deleted in MD04 for changing the Base unit of measure but when I goto change mode in MD04 , system giving an Error "Selected function cannot be used for the element "Pls let me know how to delete this entry.
Thanks & regards
Chalapathi T
Request clarification before answering.
You cannot delete from MD04, click on pegged requirement & you will know which material is calling for it. Then you need to delete it from that.
Hope it is clear.
Regards,
Vivek
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In MD04, click on the pegged requirement, you will know which material is calling for it. Now you need to open the production order / purchase order etc to delete the component if it is not required.
Or you can run MRP for the parent material via MD02 & specify the planning mode as 3. Check & revert if this resolves the problem.
Regards,
Vivek
Dear Mr.Vivek
When I goto to details of Dependent reqmt in MD04 , I can see
Planned order = NProc. I have only dependent reqmt Number . I donot have PO,Production Order numbers ,
I am running MFBF to produce main Item of this Subitem. Pls advice to delete Planned Order in this scenario
Thanks & regards
Chalapathi T
you can not delete the dep reqirement .if you deleted it will again create order proposal since it is coming from the higher level. so you have to adjust from the header level only.
For the dep requirement the system will create planned order that can be deleted
Edited by: govardhan reddy on Feb 27, 2009 7:44 AM
User | Count |
---|---|
105 | |
39 | |
6 | |
5 | |
4 | |
3 | |
3 | |
2 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.