How to create ECR?

Former Member
0 Kudos
1,080

Dear SAP Gurus,

Can any body help me with the creation steps of an Engineering Change Request (This is reuire so that every time when i change the BOM quantity the changed date (AEDAT) should get affected).

Regards

Debjeet

Edited by: Csaba Szommer on Jan 7, 2012 11:59 AM

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member928196
Active Participant
0 Kudos

Hi Macroman,

The EC management should be active in the config in OS27, and history requirement variant 1. I f you are going to use the master recipe make it 1 in OPN0.

You can create the ECR with the Tcode - CC01

Change no. status - Active

In the object types select the Bill of Material, task list, material, as per your decision as what all you want under change management and make the selections accordingly.

Regards,

Amol Kale