How to create Cost sheet

Former Member
0 Kudos

hi Gurus

now i am in a learning stage of controlling.can any body help me in preparing a cost sheet.

and what is the relation of primary cost element, secondary cost element, cost centre and internal order.

with regards

Mahesh

Accepted Solutions (0)

Answers (2)

Answers (2)

Greta
Product and Topic Expert
Product and Topic Expert
0 Kudos

The first question is answered.

The second question concerning the relation between cost elements/cost centre/internal order has been asked and answered a several times by others.

Former Member
0 Kudos

Hi,

IA costing sheet consists of one or more of the following lines:

Base lines -

These contain the amount or quantity on which the overhead is calculated.

Calculation lines -

These contain the percentage rate to be applied to one or more base lines.

Totals lines -

These contain the sum of the base amount and calculated amounts.

Costing sheets are used in the following components:

Overhead Orders (CO-OM-OPA) and Product Cost Controlling (CO-PC), where they are used to calculate overhead

Profitability Analysis (CO-PA), where they are used to calculate anticipated values

Overhead Cost Controlling (CO-OM), where they are used to calculate resource prices

Thanks