I have facing problam with activity type. when I create work cost center, then system shows "Activity type OPENER not set up for cost center GIL FDYPP004".
Please provide solution.
Thank & regards
Ajit Sharma
hi
you need to create the activity type from t-code.KL01 - Create
and you need to assign the activity type to cost centre from KP26
-ashok
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
Assign the activity type to cost center using T code KP26.
In the input screen of T code KP26 ,enter version as 0, from period 1 and to period as 12 and the Fiscal
Year as 2008 Click on Overview tab on top and key in costing details in this screen.
After performing this ,while creating the work center ,this combination of activity type & cost center
should be assigned
Activity create at KL01 assign the same at KP26 .
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ajit,
KA01 - Create Primary Cost Element for the new activities type.
KL01 - Create Activity Type tied to the primary cost element.
KP26 - Change Activity Type/Activity Price Planning - maintain the Variable price
Hope this gives you some idea.
If found useful, assign suitable points.
Rgrds,
Vivek
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
111 | |
8 | |
8 | |
6 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.