How to confirm material creation as a one activity automatically in sap ps

0 Kudos

I have a requirement to create activity in Network to confirm automatically once user create material master. Like if user creates material after it get specification requirement, once material created. how system let know one activity in PS board that material creation activity completed?

Accepted Solutions (0)

Answers (1)

Answers (1)

Ken_Melching
Product and Topic Expert
Product and Topic Expert
0 Kudos

There isn’t standard functionality to do this. You can achieve this with a SAP Workflow that starts with release of the material master the workflow will confirm a network activity.

0 Kudos

Hi Ken, If you have any sample would you please send me like screen shot or doc