I want to change to from and to lot size of the bom after saving the bom material

Accepted Solutions (0)

Answers (5)

Answers (5)

former_member7790
Participant
0 Kudos

Hi Nandha,

Screen shot you have shared in that Technical type is "blank" Simple BOM. In this case lot size field will be Hiden.

If you want to test the scenario.

Create one more alternative for the Header and technical type will be "M" Multiple BOM. In this case you will have lot size.

Regards,

Vivek

nandha
Participant
0 Kudos

okay vivek

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

Create another BOM for same material in CS01 and then check CS02.

Best Regards,

R.Brahmankar

nandha
Participant
0 Kudos

for me it is hidden

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

Create another BOM for same material in CS01 and then check CS02.

Best Regards,

R.Brahmankar

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

I think you have a single BOM for the material so changes to the lot size are ignored in the case of BOM changes as per standard SAP design.

During the creation or after creation of first alternative BOM you can set the "From/To"-area for the lot size, you can only set a base quantity too. If you add more alternatives later, you can set the "From/To"-area for the lot size of the first alternative subsequently.

Best Regards,

R.Brahmankar

lingaiahvanam
Active Contributor
0 Kudos

Hi Nandha Kumar,

You can able to change BOM lot sizes after BOM created. Go to CS02 and change the same check screenshots below.