cancel
Showing results for 
Search instead for 
Did you mean: 

how to add multiple budgets on a plant maintenance work order

former_member426924
Discoverer
0 Kudos
179

Currently we maintain single budget on each work order and and there is request from business to maintain multiple budgets since designs have multiple budgets, how can we can handle multiple budgets on single order.

View Entire Topic
a_meijer
Explorer
0 Kudos

Hi,

To my understanding this isn't possible. At least not with standard SAP functionality. The budget profile attached to PM order type will only accept one budget. Additionally you can only enter supplements or returns.

former_member426924
Discoverer
0 Kudos

Thanks for your inputs. We are planning to set up budget numbers at operation level of the order, later those costs will be settled to an internal order and finally they will interfaces to external systems like BPC, Powerplan and BW. Planning to do a proof of concept.