on 2021 Feb 03 10:02 PM
Currently we maintain single budget on each work order and and there is request from business to maintain multiple budgets since designs have multiple budgets, how can we can handle multiple budgets on single order.
Request clarification before answering.
Hi,
To my understanding this isn't possible. At least not with standard SAP functionality. The budget profile attached to PM order type will only accept one budget. Additionally you can only enter supplements or returns.