Hi Gurus,

I need a solution for below scenerio

HALB mat.is produced and then painted (let's say waterswitch) then it becomes FERT but how can I implement this in system ?what is the best way?

Thanks in advance

View Entire Topic
Former Member
0 Kudos

Hi,

     The best way to convert HALB to FERT by using production order rather than material to material stock transfer.

Create material master for FERT(Procurement type = In-house) and BOM for the same.

follow the standard procedure for the production ie. convertion of planned order to production order, confirmation and Goods receipt of the material.

By this way you can also include the paint cost for the material.

Regards,