on 2010 May 27 1:38 PM
Hi Experts,
We are in post go live support stage.
Error ;
When we are delimiting the position in OM.
It is asking Request Number. How to overcome this.
Please provide me the answer.
Thanks & Regards,
Vinay
Hi Vinay,
Go to table T77S0 via SM30.
Make sure that TRSP CORR is X .
Regards,
Dilek
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Dilek,
Thanks for the reply,
I have one more doubt...As am into first implementation.
The solution what you have provided, that we need to do those steps in the development server then that request we should move to the production..then my solve will solve or not
Please reply.
Thanks & Regards,
Vinay
With my solution, you won't be having request anymore.
However, if you want to create the org structure in development system and transport it into production, leave the settings as is.
Generally, I do prefer maintaining organizational structure directly in production system.
In development system, I only create an org structure for testing purposes.
Regards,
Dilek
User | Count |
---|---|
109 | |
8 | |
8 | |
6 | |
5 | |
5 | |
5 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.