on 2012 Feb 13 3:46 PM
Hi Friendz...
I need a solution for a business process ! My client needs to edit enquiry after referring enquiry to quotation during sales order processing, It's under make to order process. Because costing is done only at Enquiry level. Can u guys Plz Suggest me ?
Thanks In Advance...
Hi,
First go to T.code VOV7 select your inquiry item category (AFN) in that make Completion Rule field blank,
next go to T.code VTAA select your quotation and inquiry,at the header level un tick the complete reference check box.
check and revert,
Regards,
Ram