I have an outbound delivery that I can not post goods issue in VL02N. It is give me

Deficit of Project stock QI 1 PC.

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member

Thank you all, the issue was in the purchase order. On the line that was getting return the delivery tab, it had the wrong stock type. It should had unrestricted use not quality inspection. Once that was change it let me post good issue.

ankurch
Active Contributor
0 Kudos

Please close the thread, by selecting your answer as correct.

To close thread!

Thanks,

ankurch
Active Contributor

Hi Jose,

Please check stock of material is available in the same plant/storage location in in-restricted use of stock!

thanks,

former_member197616
Active Contributor
0 Kudos

Hi,

If not please post a Transfer Post from Unrestrcited stock to project stock against the Project WBS .

Regards

vijay2006ece
Contributor
0 Kudos

Hi Jose,

Please verify the stock in that particular Plant/Sloc/Project/Batch/etc combination mentioned in the outbound delivery.

If stock is available, System can post/move the stock.